Scope
The majority of the works were undertaken beneath ground level and were served by temporary hoists installed in a fully enclosed secure structure.
Challenge
Parts of both buildings remained in full operation so the interfaces with the buildings users and the general public was one of the most challenging parts of the scheme. Identifying this interface very early on meant employing additional management to specifically control this element.
When complete the library benefitted from 4 new lifts, new reception area, toilets and an open plan book store with individual reading booths.
- Strategic Construction
- Design Co-ordination
- Engineering
Related Project Profiles
Let's do something great on your next project.
Contact UsImportant Note.
Lyndon SGB rebranded to Brand Access Solutions on February 4, 2025.
Projects were delivered at the time under the trading names of: Lyndon SGB, SGB, Lyndon Scaffolding or Taylor’s Hoists.