Scope
Prime was awarded a construction/fit-out contract for the refurbishment and fit-out of the BMI check in desks at Terminal 3. The company installed additional check-in desks and reconfigure the departure area and lounges. This included installing new partitions, desks, ceilings, floors and walling.
Challenge
In addition, Prime also carried out the removal of asbestos and the subsequent refurbishment of the Tower Block level 7 which involved installing new ceilings, walls, floors, new column cladding and application of bomb film to all windows.
- Asbestos removal
- Temporary works engineering
- Refurbishment and fit-out services
- Contract Duration: 9 months