Scope
The esteemed customer is specialist FLO (Ferrovial Agroman & Laing O’Rourke), with works commencing in October 2017 & still on-going 24:7:365.
Challenge
The access solutions provided are genuine CUPLOK® materials along with MkII Solider components to form heavy-duty gallows brackets, supporting the structure every 8m (mechanically fixed to the shaft wall using chemical anchors). The scaffold was built by suspending lift-by-lift as the 54m deep shaft was excavated.
We supplied & installed the 54m suspended staircase access and offered weekly site inspections in the tunnels.
The structure was designed in-house with the drawings being supported by detailed calculations and CAT certification. The design package was subject to a category 2 design check, before we supplied and progressively installed the 54m suspended staircase access. The scaffold was handed over in completed sections – the completed sections being subject to schedule 7 statutory inspection.
It’s another great example of our nationwide ability to meet the exacting demands of our clients; safely & with consistent, quality… all managed for the customer in-house.
Related Project Profiles
Let's do something great on your next project.
Contact UsImportant Note.
Lyndon SGB rebranded to Brand Access Solutions on February 4, 2025.
Projects were delivered at the time under the trading names of: Lyndon SGB, SGB, Lyndon Scaffolding or Taylor’s Hoists.