The Jewish Community Centre, London | Hoists

Brand Access Solutions are supplying a driver-less 650 20/32 Passenger Goods Hoist to the new construction of a Jewish Community Centre in the Finchley Rd, North London.

Jewish Community Centre

Scope

The hoist comprises of 9 landings covering a total height of 28.5 metres and will be on site for a total of 20 weeks. This is 1 of 3 projects that Brand Access Solutions are currently carrying out for BAM Construction.

Challenge

  • Driver-less 650 20/32 Passenger Goods Hoist
  • Contract Duration: 20 weeks